Petrobras has just released its 2026–2030 Strategic Plan, and as the driving force of the offshore industry, it becomes essential to update the market on the next FPSO units expected in Brazil.


FPSO P-78 – 2025

Conteúdo do artigo
FPSO PETROBRAS P78

The FPSO P-78 is the sixth development project in the Búzios field, the largest ultra-deepwater asset in the world. With first oil expected in December 2025, this unit is central to Petrobras’ plan to lift production in Búzios to 1.6 million barrels per day by the end of the decade.

The vessel was delivered by Seatrium. Its construction involved a new hull built by Hyundai Heavy Industries in South Korea, key topsides modules fabricated at BrasFELS (Angra dos Reis, Brazil), and final integration in Singapore.

In a notable logistical move, the unit sailed from Singapore to Brazil with crew onboard, allowing commissioning work to continue during transit and advancing the production start by roughly two weeks. The platform arrived at its location in Búzios on September 30, 2025, and is currently completing subsea hook-up activities.

Designed to operate in the Santos Basin pre-salt at depths of up to 2,100 meters, the P-78 can produce 180,000 bpd and process 7.2 million m³ of gas per day. The project belongs to the Búzios Consortium, led by Petrobras (operator with 88.99%), alongside Chinese partners CNOOC (7.34%) and CNODC (3.67%), with PPSA managing the production-sharing contract.


FPSO P-79 – 2026

Conteúdo do artigo
PETROBRAS FPSO P79

The FPSO P-79 is the eighth permanent unit allocated to the Búzios field and the “sister vessel” of the P-78. Both units were developed under Petrobras’ Reference Basic Design (PBREF) model and share the same production capacity: 180,000 barrels of oil and 7.2 million m³ of gas per day. However, they differ significantly in execution strategy and contractor structure.

While the P-78 was delivered by Seatrium, the P-79 was awarded to a joint venture between Italy’s Saipem and South Korea’s DSME (now Hanwha Ocean). Key distinctions include:

The vessel departed South Korea on November 11, 2025. Like the P-78, it is crossing the ocean with commissioning teams onboard, enabling early testing and shortening the ramp-up phase upon arrival in Brazil, expected in early 2026.


FPSOs P-80, P-82 and P-83 – 2027

Conteúdo do artigo
HUL PETROBRAS FPSO P80/ CIMC RAFFLES

The P-80, P-82 and P-83 are part of the next development wave for the Búzios field in the Santos Basin pre-salt:

These are among the largest FPSOs ever deployed in the global industry. All three share similar high-performance specifications:

Petrobras adopted the EPC (Engineering, Procurement and Construction) contracting model. Due to the merger between Singapore’s shipyard giants, the projects ended up under Seatrium (Keppel + Sembcorp), though originally:

Start-up is scheduled for 2027.

A major highlight of this trio is their “green platform” design, focused on lowering carbon emissions through:


FPSO Raia – 2028

Conteúdo do artigo
FPSO RAIA HULL / REPSOL SINOPEC

The Raia Project goes beyond a conventional FPSO. The unit will be capable of exporting 16 million m³/day of pipeline-spec natural gas directly to the domestic market — essentially functioning as a floating gas processing plant — connected by a 200 km pipeline to shore.

A R$ 2 billion contract between Equinor and Tenaris ensured 99% local content for the pipe supply, all already delivered.

The former BM-C-33 area includes the Pão de Açúcar, Gávea and Seat fields. The Raia Consortium is operated by Equinor (35%), with Repsol Sinopec Brazil (35%) and Petrobras (30%). The project targets an exceptionally low carbon intensity of 6 kg CO₂ per barrel.

Conteúdo do artigo
TIMELINE FOR THE FPSO RAIA/ REPSOL SINOPEC

FPSOs P-84 and P-85 – 2029 & 2030

Conteúdo do artigo
PETROBRAS FPSO P84

The P-84 (Atapu-2) and P-85 (Sépia-2) are set to become the largest FPSOs ever built for Petrobras, each designed for 225,000 bpd. A key differentiator is their dedicated natural gas export capacity of 10 million m³/day, unlike other recent projects focused primarily on reinjection.

A US$ 8.15 billion contract was awarded to Seatrium. First oil is expected between 2029 and 2030. Hull fabrication is being carried out by CIMC Raffles in China, with module integration split between Brazil (Seatrium Aracruz) and Singapore.

Innovation — “All-Electric” Concept

To reduce emissions by roughly 30%, the design incorporates:

Consortium Structure

P-84 (Atapu): Petrobras 65.7%, Shell 16.7%, TotalEnergies 15%, Petrogal 1.7%, PPSA 0.9%

P-85 (Sépia): Petrobras 55.3%, TotalEnergies 16.9%, Petronas 12.7%, QatarEnergy 12.7%, Petrogal 2.4%


FPSO Gato do Mato – 2029

Conteúdo do artigo
FIRST STEEL CUT CEREMONY – MODEC

After canceling the 2022 tender due to cost inflation, Shell redesigned the project during 2023–2024. The Final Investment Decision was taken in March 2025, followed by the declaration of commerciality in July 2025, renaming the unitized area as the Orca Field.

The consortium — Shell (70%) and Ecopetrol (30%) — selected MODEC to build the FPSO, with first oil planned for 2029.


Barracuda & Caratinga Revitalization FPSO – 2031+

Conteúdo do artigo
BARRACUDA & CARATINGA MAP

The revitalization of Barracuda and Caratinga underwent major restructuring after the initial tender failed. Only one bid was received (Shapoorji Pallonji), at prohibitively high cost, leading Petrobras to cancel the process in 2024.

The new strategy relies on:


Albacora Revitalization FPSO – 2031+

Conteúdo do artigo
ALBACORA FIELD

The project aims to replace aging units P-25 and P-31 with a new FPSO able to produce 120,000 bpd, unlocking both post-salt reserves and the pre-salt Forno structure.

Due to market constraints, Petrobras shifted from a charter model to BOT and postponed proposal submissions to May 25, 2026. Furthermore, the 2026–2030 Strategic Plan removed Albacora from the current five-year horizon, pushing first oil beyond 2030 and raising concerns about production gaps as P-25/P-31 near retirement.


Marlim Leste / Marlim Sul Revitalization FPSO – 2031+

Conteúdo do artigo
MARLIM LESTE
Conteúdo do artigo
MARLIM SUL

Revitalization and Asset Replacement

The revitalization plan for the Marlim Sul and Marlim Leste fields aims to modernize production and extend the operational lifespan of these assets. The new unit under development (P-86) is intended to replace the current platforms P-38, P-40, P-53 and the FPSO Cidade de Niterói.

Status of the P-86 (Cost-Reduction Focus) Despite its strategic relevance in replacing these four units, the P-86 project has undergone significant restructuring:

The P-86 unit will replace platforms P-38, P-40, P-53 and FPSO Cidade de Niterói. However, the tender was suspended due to excessive capital costs, and the project returned to basic engineering for redesign and cost reduction.


SEAP 1 & SEAP 2 – 2030 and 2031+

Conteúdo do artigo
SEAP 1 E SEAP 2 – BRASIL ENERGIA

After years of setbacks, Petrobras finally awarded SBM Offshore the contracts for SEAP I and SEAP II in November 2025 under the BOT model. The bids of approximately US$ 4.1 and US$ 4.3 billion respectively were strengthened by SBM’s standardized Fast4Ward hull design, supporting delivery by 2030.

These units will be transformative for the state of Sergipe, providing:

They are expected to restart industrial activity in the region and enable workers previously relocated to Rio/Macaé to return home.


FPSO P-91 (Búzios 12) – 2031+

Conteúdo do artigo

The new unit will become the 12th platform assigned to the Búzios field, reinforcing its position as the company’s largest producing asset and further strengthening its role in supplying natural gas to the country.

The newly announced P-91 will act as a gas-processing hub for Búzios, treating and exporting gas to shore — including volumes from units without processing capability. With five new FPSOs on the way, Búzios will host an unprecedented 12 producing units in a single field.


FPSO Mero Extension – 2031+

Project under evaluation.


FPSO Entorno de Forno – 2031+

Project under evaluation.


FPSO Tupi Revitalization – 2031+

Project under evaluation.


FPSO ICSPB – 2031+

Project under evaluation.


RESEARCH & AUTHORSHIP CREDITS: Vitor Padua


Learn more about how Inovaren can help in this projects ate www.inovaren.com